DG refuelling fuel verification case study visual for a hydroelectric project
By: Aether June 12, 2026

Hydroelectric Project Refueling Fraud Case Study: Closing the Gap Between Dispensed and Received Diesel

The Challenge

At a remote hydroelectric project site, operations relied on a set of approximately 10–15 diesel generators, predominantly 2000 kVA units supplemented by lower-capacity DGs, to support critical equipment, site offices, and project activities.

In such environments, diesel becomes one of the largest operating expenses. While refuelling records can confirm how much fuel was dispensed, they cannot verify whether the fuel actually reached the generator tank. Without tank-level monitoring and fuel reconciliation, significant fuel losses can remain undetected.

The Challenge — DG refuelling accountability gap at hydroelectric project site

Monthly Inspection Revealed Project Health Status Issues

As part of Aether's monthly site health inspection program, our team reviewed the fuel monitoring assets installed across the project.

The monthly health review indicated that the overall health status of the project's fuel monitoring system was below the recommended level. A detailed health report was shared with the customer, highlighting the identified issues and recommending corrective actions to improve health status.

Based on the findings, Aether recommended deploying a service engineer to carry out the required service activities. The customer accepted the recommendation and requested on-site support to address the identified issues.

Accordingly, a service engineer was deployed to the site to attend the service request & maintenance activities.

Unusual Resistance During Rectification

Upon arrival, the site team informed our engineer that the Fuel Monitoring System (FMS) had been removed following a major incident.

To understand the issue, Aether requested supporting documentation, such as an incident report or technical findings linking the problem to the fuel monitoring system. However, no such documentation was available.

Despite this, the P&M assistant team continued to resist rectification.

The matter was escalated to the Plant & Machinery (P&M) Head. Aether communicated that if there was a genuine product-related issue, we would investigate and take responsibility. As no supporting evidence could be provided, the P&M team authorized Aether to proceed with the rectification and recommissioning of the fuel monitoring system.

Unusual resistance during FMS rectification at site

The Resistance That Triggered Further Investigation

Following the recommissioning of the fuel monitoring system, Aether’s Onsite Support and AE-BI teams found the earlier resistance suspicious. A site fighting this hard to keep its own fuel monitoring switched off, with nothing on paper to justify it, isn’t a technical problem — it’s a behavioural one. So we looked closer.

As part of this process, we requested the site’s diesel refuelling records for reconciliation. Before sharing the data, the P&M team conducted their own comparison between the refuelling records and the fuel data available on the Aether platform.

Based on this initial review, they observed discrepancies and raised concerns that the fuel sensors might not be functioning correctly. They approached Aether stating that the refuelling records were not matching the fuel received data shown on the platform.

To investigate the matter further, Aether requested the complete refuelling records from the site. Our objective was to perform a detailed transaction-level reconciliation to determine whether the discrepancies were caused by sensor inaccuracies or by differences between fuel dispensed and fuel actually received by the generators.

This request marked the beginning of a comprehensive fuel reconciliation exercise.

What the Data Revealed

A complete reconciliation was performed between bowser dispensing records and actual fuel received by the monitored DG sets.

The analysis revealed significant differences:

  • Completely Missing Fuel Events: Fuel was recorded as delivered, but the generator tank showed no increase in fuel level.
  • Multiple Entries for a Single Fuel Fill: Several refuelling records were created for what appeared to be a single fuel filling event, resulting in higher recorded fuel quantities than actually received.
  • Fuel Delivered vs Fuel Received Mismatch: The fuel quantity recorded by the vendor was higher than the fuel actually received in the generator tank.
  • Approximately: 17,000–18,000 litres of diesel could not be accounted for within a single month.

This analysis was performed on only a subset of the project's DG fleet, representing roughly one-third of the total generators operating at the site, indicating that the overall exposure could have been significantly higher.

Since the generators were owned by the project, every litre of unaccounted diesel directly impacted the project’s operating budget.

What the fuel reconciliation data revealed

Need Site-Level Fuel Accountability?

If your team is seeing dispensing gaps, refuel variance, or fuel costs that don’t square with output, Aether can help map the right fuel monitoring setup for your sites.

Validating the Findings

Since the discrepancies identified during the reconciliation exercise were significant, the customer wanted to ensure that the fuel monitoring system was functioning correctly before drawing any conclusions.

To verify the accuracy of the system, Aether conducted validation tests in the presence of site personnel.

Witnessed Refuelling Test

A controlled refuelling activity was carried out with the generator switched off and site personnel present. The quantity recorded by the fuel monitoring system closely matched the actual volume dispensed, achieving an accuracy of 99.99%.

Cross-Verification of Refuelling Events

The Aether team also reviewed multiple genuine refuelling transactions and compared the dispensed quantity with the fuel received in the tank. In these cases, the fuel-level data consistently aligned with the actual refuelling records within an acceptable tolerance range.

Validation Outcome

The validation exercise confirmed that the fuel monitoring system was operating correctly and accurately measuring fuel received by the generators. The witnessed refuelling test, which demonstrated 99.99% measurement accuracy, provided confidence that the discrepancies identified during the reconciliation process were genuine and not the result of sensor inaccuracies.

Validating findings with witnessed refuelling test

Results and Business Impact

The project moved from suspicion to verified evidence.

By reconciling dispensing records with actual tank-level data, the customer was able to identify approximately ₹15–16 lakh worth of unaccounted diesel within a single month.

The findings provided the project team with a defensible, data-backed basis for further investigation and corrective action.

₹15–16 lakh

Unaccounted diesel identified in a single month

Following the study:

  • Fuel discrepancies were quantified and verified.
  • The customer initiated corrective actions.
  • Fuel reconciliation became a recurring monthly review process rather than a one-time audit.
  • The project gained greater visibility and accountability over diesel consumption across its DG fleet.

Following the corrective actions, the site reported that the previously observed refuelling discrepancies were no longer occurring, indicating that the source of the losses had been effectively addressed.

The case demonstrated how combining fuel-level monitoring with systematic refuelling reconciliation can transform fuel management from a record-keeping exercise into a measurable operational control process.

Results and business impact — closing the fuel accountability gap

Want to implement similar controls across your sites?

See how Aether’s refuelling reconciliation turns dispensing records into verified fuel accountability across your fleet.